Construction & Maintenance of new Berths and Maintenance of existing Berths at Khiran Touristic Park – State of Kuwait.

Client: Touristic Enterprises Co. – Kuwait
Contract no.: 1271/2009
Commencement date: 01/01/2010
Completion date:  02/03/2013

Brief Description of the project : Demolition of existing marina,Construction of protection wall of steel sheet piles tied with rods capped with reinforced concrete,backfill behind wall with dolomite blocks and formation of concrete deck covered with interlock tiles and landscaping yards.Construction of 4 service buildings of two floors each along with access roads and landscaping works,kerbstones and interlock tiles.Construction of new Berths with concrete floaters pontoon ,equipped with a prepaid system of all services such as water supply, fire fighting system,sewer system and all related electrical works.

Marine Jetty and Hose Repair Works at Mina Saud –  State of Kuwait.

Client:Saudi Arabian Chevron – Kuwait
Contract no.: SAT – 216R
Commencement date:  13/05/2007
Completion date:  12/12/2008

Brief Description of the project : Repair of existing jetty of 200m length and 6m width.Renovation of underneath steel structure in terms of grid blasting, welding and epoxy paint works,concrete repair works along with asphalt works.Handrail supply and installation,supply and install of Fire fighting system including pipes and pumps and supply and installation of loader crane as well.

Banjul International Airport Improvement Project-Phase II,Banjul – The Gambia.

Client: Gambia Civil Aviation Authority
Contract no.: AVG27/259/0268
Commencement date: 01/01/2015
Completion date:  01/07/2016

Brief Description of the project : Rehabilitation and Extension of the existing Apron , construction of two new Taxiways with asphalt surface along with Airfield lighting and airside roads.The works included resealing to apron joints,replacing the defected concrete slabs,expansion the Apron by rigid concrete slabs,milling and asphalt surfacing to existing taxiways ,various civil works around the fire fighting station,drainage works and electrical works related to Airfield and airside lighting, such as control panel boards,guidance signs,cabling and all associated electrical infrastructure Works.